Design team · Thursday, July 3

Website Redesign

At risk

Critical path runs through the token export — “Homepage hero” has been blocked 4 days, and it’s the thing standing between here and the Aug 2 launch.

Done
12
Blocked
3
1 on the critical path
Due this week
4
2 depend on the hero
Health
At risk
Otto's read, updated 7:00 AM

12 done vs. ~15 needed today to stay on pace.

At-risk tasks 3
Homepage heroBlocked 4dBlocked byDesign System 2.0
P
Responsive nav + mobile menuIdle · waits on hero
M
Testimonials carouselIdle · waits on hero
S
Otto’s project briefread-only
for you · assembled 7:00 AM
Critical path runs through the token export; hero slips the Aug 2 date unless the dependency splits or the hero re-dates to when the export lands.
Source
Read-only · nothing to undo
See the dependency chain on the timeline →
Milestones
Design tokens exportthis weekJul 4
Homepage hero completeat riskJul 5
Dev QA passJul 22
Launch — site freezecriticalAug 2
Activity
A
Amara OseiJun 30
Parking my art until the new tokens land — @Priya heads up.
Marco attached hero-v3.png· Jul 1
Ottoread-onlyToday, 7:00 AM
Flagged the token dependency as the critical-path risk.